PP1190002501137

Aditya Nagri 1 · Nagpur (M Corp.), Nagpur · Aditya Developers

Promised for 31 Dec 2028, extended to 30 Apr 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2028 to 30 Apr 2029.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Oct 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about PP1190002501137

Is Aditya Nagri 1 delayed?

Its completion moved from 31 Dec 2028 to 30 Apr 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PP1190002501137. The completion date moved from 31 Dec 2028 to 30 Apr 2029.

Who is the promoter?

MahaRERA records Aditya Developers as the promoter of PP1190002501137.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PP1190002501137.

Answers are generated from the record.