RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
PM1330002501751
Haware Amber Hills · Thane (M Corp.), Thane · Haware's Housing Development Finance Corporation Ltd
Promised for 25 Dec 2030, extended to 25 Apr 2031, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 25 Dec 2030 to 25 Apr 2031.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about PM1330002501751
Is Haware Amber Hills delayed?
Its completion moved from 25 Dec 2030 to 25 Apr 2031; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for PM1330002501751. The completion date moved from 25 Dec 2030 to 25 Apr 2031.
Who is the promoter?
MahaRERA records Haware's Housing Development Finance Corporation Ltd as the promoter of PM1330002501751.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names PM1330002501751.
Answers are generated from the record.
