Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredMahaRERA status: Certificate Signed

PM1220002602200

Ashapuri Kasturi · Nashik · Rishi Builders & Developers

Promised for 31 Aug 2030 and not extended so far.

3 years and 10 months to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate8 Oct 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about PM1220002602200

Is Ashapuri Kasturi delayed?

Not so far. MahaRERA records a promised completion of 31 Aug 2030, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PM1220002602200.

Who is the promoter?

MahaRERA records Rishi Builders & Developers as the promoter of PM1220002602200.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PM1220002602200.

Answers are generated from the record.

Data through25 Oct 2026, 03:34SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology