RegisteredExtendedMahaRERA status: Certificate Signed

P99000078363

Damodar Park C Bldg · Vasaivirar City (M Corp), Palghar · Parshwanath Developers

Promised for 31 Dec 2029, extended to 30 Apr 2030, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2029 to 30 Apr 2030.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate6 Dec 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000078363

Is Damodar Park C Bldg delayed?

Its completion moved from 31 Dec 2029 to 30 Apr 2030; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P99000078363. The completion date moved from 31 Dec 2029 to 30 Apr 2030.

Who is the promoter?

MahaRERA records Parshwanath Developers as the promoter of P99000078363.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000078363.

Answers are generated from the record.

Data through28 Oct 2026, 03:07SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology