Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P99000078005

Platinum Aura Wing A · Vasaivirar City (M Corp), Palghar · Platinum Realtech Llp

Promised for 31 Jul 2029, extended to 30 Nov 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Jul 2029 to 30 Nov 2029.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate19 Nov 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000078005

Is Platinum Aura Wing A delayed?

Its completion moved from 31 Jul 2029 to 30 Nov 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P99000078005. The completion date moved from 31 Jul 2029 to 30 Nov 2029.

Who is the promoter?

MahaRERA records Platinum Realtech Llp as the promoter of P99000078005.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000078005.

Answers are generated from the record.

Data through25 Oct 2026, 03:23SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology