Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P99000055349

Saravali Classic · Saravali, Palghar · Maverick Builders And Developers

Promised for 31 Dec 2028, extended to 30 Apr 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2028 to 30 Apr 2029.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate18 Mar 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000055349

Is Saravali Classic delayed?

Its completion moved from 31 Dec 2028 to 30 Apr 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P99000055349. The completion date moved from 31 Dec 2028 to 30 Apr 2029.

Who is the promoter?

MahaRERA records Maverick Builders And Developers as the promoter of P99000055349.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000055349.

Answers are generated from the record.

Data through25 Oct 2026, 03:19SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology