RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P99000051425

Jasmin Paradise · Palghar · Jasmin Developers

Promised for 31 May 2025, extended once to 31 May 2026 — and that date has passed without the project marked complete on MahaRERA.

1 year and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 May 2025 to 31 May 2026 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 May 2026, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate14 Jun 2023View
Extension certificate20 Aug 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000051425

Is Jasmin Paradise delayed?

Yes. MahaRERA records a promised completion of 31 May 2025, revised to 31 May 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P99000051425. The completion date moved from 31 May 2025 to 31 May 2026.

Who is the promoter?

MahaRERA records Jasmin Developers as the promoter of P99000051425.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000051425.

Answers are generated from the record.

Data through30 Oct 2026, 02:53SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology