RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P99000051399
Shambhavi Apartments · Ashagad, Palghar · Jayesh Balvant Jani
Promised for 30 Dec 2028, extended to 30 Apr 2029, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2028 to 30 Apr 2029.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P99000051399
Is Shambhavi Apartments delayed?
Its completion moved from 30 Dec 2028 to 30 Apr 2029; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P99000051399. The completion date moved from 30 Dec 2028 to 30 Apr 2029.
Who is the promoter?
MahaRERA records Jayesh Balvant Jani as the promoter of P99000051399.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P99000051399.
Answers are generated from the record.
