Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P99000049405

Trinity Oasis · Chandrapada, Palghar · Harsh Tirupati Developers Llp

Promised for 30 Sep 2026 — that date has passed and MahaRERA does not mark the project complete.

1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Sep 2026, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate8 Feb 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000049405

Is Trinity Oasis delayed?

Yes. MahaRERA records a promised completion of 30 Sep 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P99000049405.

Who is the promoter?

MahaRERA records Harsh Tirupati Developers Llp as the promoter of P99000049405.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000049405.

Answers are generated from the record.

Data through25 Oct 2026, 03:12SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology