P99000023465

Sai City Bungalow Scheme · Vasaivirar City (M Corp), Palghar · Shree Sai Construction Co

Promised for 30 Oct 2025 — that date has passed and MahaRERA does not mark the project complete.

1 year past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Oct 2025, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate8 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000023465

Is Sai City Bungalow Scheme delayed?

Yes. MahaRERA records a promised completion of 30 Oct 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P99000023465.

Who is the promoter?

MahaRERA records Shree Sai Construction Co as the promoter of P99000023465.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000023465.

Answers are generated from the record.

Data through25 Oct 2026, 02:41SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology