Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P99000019030

Raj Emerald · Vasaivirar City (M Corp), Palghar · Raj Homemakers Llp

Promised for 1 Dec 2022 — that date has passed and MahaRERA does not mark the project complete.

3 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 1 Dec 2022, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000019030

Is Raj Emerald delayed?

Yes. MahaRERA records a promised completion of 1 Dec 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P99000019030.

Who is the promoter?

MahaRERA records Raj Homemakers Llp as the promoter of P99000019030.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000019030.

Answers are generated from the record.

Data through29 Oct 2026, 02:05SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology