Dattaganga · Palghar · Ganesh Land Developers And Construction Private Limited
Promised for 15 Feb 2021, extended once to 25 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.
5 years and 8 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 15 Feb 2021 to 25 Dec 2024 (1 extension certificate on record).
- !Risk: The latest completion date on record, 25 Dec 2024, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P99000018314
Is Dattaganga delayed?
Yes. MahaRERA records a promised completion of 15 Feb 2021, revised to 25 Dec 2024, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P99000018314. The completion date moved from 15 Feb 2021 to 25 Dec 2024.
Who is the promoter?
MahaRERA records Ganesh Land Developers And Construction Private Limited as the promoter of P99000018314.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P99000018314.