RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P99000014701
Mahavir Shopping Centre · Umroli, Palghar · Mahavir Builders & Developers
Promised for 30 Dec 2022, extended once to 30 Dec 2023 — and that date has passed without the project marked complete on MahaRERA.
3 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2022 to 30 Dec 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Dec 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P99000014701
Is Mahavir Shopping Centre delayed?
Yes. MahaRERA records a promised completion of 30 Dec 2022, revised to 30 Dec 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P99000014701. The completion date moved from 30 Dec 2022 to 30 Dec 2023.
Who is the promoter?
MahaRERA records Mahavir Builders & Developers as the promoter of P99000014701.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P99000014701.
Answers are generated from the record.