P99000010275
Paramount Heights · Vasaivirar City (M Corp), Palghar · Zion Constructions
Promised for 30 Jun 2021, extended once to 29 Jun 2023 — and that date has passed without the project marked complete on MahaRERA.
5 years and 4 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2021 to 29 Jun 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 29 Jun 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P99000010275
Is Paramount Heights delayed?
Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 29 Jun 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P99000010275. The completion date moved from 30 Jun 2021 to 29 Jun 2023.
Who is the promoter?
MahaRERA records Zion Constructions as the promoter of P99000010275.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P99000010275.