RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P99000004430

Divine Residency · Vasaivirar City (M Corp), Palghar · Guruprabhu Builders And Developers

Promised for 31 Aug 2019, extended once to 28 Aug 2022 — and that date has passed without the project marked complete on MahaRERA.

7 years and 2 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Aug 2019 to 28 Aug 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 28 Aug 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Aug 2017View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000004430

Is Divine Residency delayed?

Yes. MahaRERA records a promised completion of 31 Aug 2019, revised to 28 Aug 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P99000004430. The completion date moved from 31 Aug 2019 to 28 Aug 2022.

Who is the promoter?

MahaRERA records Guruprabhu Builders And Developers as the promoter of P99000004430.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000004430.

Answers are generated from the record.

Data through29 Oct 2026, 01:51SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology