Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P99000003885
Rg-A,b,e,f · Vasaivirar City (M Corp), Palghar · Reliable Realtouch
Promised for 25 Dec 2019, extended once to 31 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.
6 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 25 Dec 2019 to 31 Dec 2025 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Dec 2025, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P99000003885
Is Rg-A,b,e,f delayed?
Yes. MahaRERA records a promised completion of 25 Dec 2019, revised to 31 Dec 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P99000003885. The completion date moved from 25 Dec 2019 to 31 Dec 2025.
Who is the promoter?
MahaRERA records Reliable Realtouch as the promoter of P99000003885.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P99000003885.