RegisteredCompletion date passedMahaRERA status: Certificate Signed

P53100053046

Galaxy Sky · Sangli Miraj Kupwad (M Corp.), Sangli · Sky Galaxy Constructions

Promised for 31 May 2026 — that date has passed and MahaRERA does not mark the project complete.

5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 May 2026, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate12 Oct 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P53100053046

Is Galaxy Sky delayed?

Yes. MahaRERA records a promised completion of 31 May 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P53100053046.

Who is the promoter?

MahaRERA records Sky Galaxy Constructions as the promoter of P53100053046.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P53100053046.

Answers are generated from the record.

Data through25 Oct 2026, 03:07SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology