RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P53100053046
Galaxy Sky · Sangli Miraj Kupwad (M Corp.), Sangli · Sky Galaxy Constructions
Promised for 31 May 2026 — that date has passed and MahaRERA does not mark the project complete.
5 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Risk: The latest completion date on record, 31 May 2026, has passed.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P53100053046
Is Galaxy Sky delayed?
Yes. MahaRERA records a promised completion of 31 May 2026, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P53100053046.
Who is the promoter?
MahaRERA records Sky Galaxy Constructions as the promoter of P53100053046.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P53100053046.
Answers are generated from the record.
