RegisteredCompletion date passedMahaRERA status: Certificate Signed

P53100013539

Kanchan Ratna · Sangli Miraj Kupwad (M Corp.), Sangli · V D Vaje Builders & Developers

Promised for 31 Aug 2019 — that date has passed and MahaRERA does not mark the project complete.

7 years and 2 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Aug 2019, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Oct 2017View

Orders 0

No MahaRERA order or list names this number.

Questions about P53100013539

Is Kanchan Ratna delayed?

Yes. MahaRERA records a promised completion of 31 Aug 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P53100013539.

Who is the promoter?

MahaRERA records V D Vaje Builders & Developers as the promoter of P53100013539.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P53100013539.