Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52900010635

Siddhidata Park · Oras Bk., Sindhudurg · Abhijit Prakash Jaitapkar

Promised for 30 Sep 2019, extended once to 8 Mar 2022 — and that date has passed without the project marked complete on MahaRERA.

7 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Sep 2019 to 8 Mar 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 8 Mar 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate31 Aug 2017View
Extension certificate18 Jan 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P52900010635

Is Siddhidata Park delayed?

Yes. MahaRERA records a promised completion of 30 Sep 2019, revised to 8 Mar 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52900010635. The completion date moved from 30 Sep 2019 to 8 Mar 2022.

Who is the promoter?

MahaRERA records Abhijit Prakash Jaitapkar as the promoter of P52900010635.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52900010635.

Answers are generated from the record.

Data through25 Oct 2026, 02:06SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology