Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P52100080236

Adhishree Elite · Jalochi, Pune · Bhosale Nazirkar Developers

Promised for 31 Dec 2027, extended to 30 Apr 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2027 to 30 Apr 2028.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate13 May 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100080236

Is Adhishree Elite delayed?

Its completion moved from 31 Dec 2027 to 30 Apr 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100080236. The completion date moved from 31 Dec 2027 to 30 Apr 2028.

Who is the promoter?

MahaRERA records Bhosale Nazirkar Developers as the promoter of P52100080236.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100080236.

Answers are generated from the record.

Data through25 Oct 2026, 03:26SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology