RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100053683
Madhumati Chsl · Shivajinagar Bhamburda, Pune · Kotibhaskar Infrastructures &Developers Pvt.Ltd
Promised for 30 Sep 2026, extended once to 30 Jan 2027, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Sep 2026 to 30 Jan 2027 (1 extension certificate on record).
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100053683
Is Madhumati Chsl delayed?
Its completion moved from 30 Sep 2026 to 30 Jan 2027; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100053683. The completion date moved from 30 Sep 2026 to 30 Jan 2027.
Who is the promoter?
MahaRERA records Kotibhaskar Infrastructures &Developers Pvt.Ltd as the promoter of P52100053683.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100053683.
Answers are generated from the record.