DeregisteredCompletion date passedMahaRERA status: Certificate Signed

P52100052207

Noble Heights · Pune City, Pune · Noble Developers

Promised for 31 Dec 2025 — that date has passed and MahaRERA does not mark the project complete.

10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2025, has passed.
  • Risk: MahaRERA lists this registration as deregistered.
  • Clear: Completion date never extended.

Documents 1

Registration certificate31 Jul 2023View

Orders 1

Deregistered

Deregistered: NOBLE HEIGHTS

matched by RERA number

View order →

Questions about P52100052207

Is Noble Heights delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100052207.

Who is the promoter?

MahaRERA records Noble Developers as the promoter of P52100052207.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P52100052207.

Answers are generated from the record.

Data through25 Oct 2026, 03:03SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology