Registered1 extensionMahaRERA status: Certificate Signed

P52100052123

Shriram Skypark · Charholi, Pune · Shriram Samruddhi Developers

Promised for 22 Dec 2025, extended once to 25 Jun 2027, which is still ahead.

The revised date is 1 year and 6 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 22 Dec 2025 to 25 Jun 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate24 Jul 2023View
Extension certificate29 May 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100052123

Is Shriram Skypark delayed?

Its completion moved from 22 Dec 2025 to 25 Jun 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100052123. The completion date moved from 22 Dec 2025 to 25 Jun 2027.

Who is the promoter?

MahaRERA records Shriram Samruddhi Developers as the promoter of P52100052123.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100052123.

Answers are generated from the record.

Data through25 Oct 2026, 03:07SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology