Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passedExtendedMahaRERA status: Certificate Signed

P52100048886

Shikrapur Trade Center Phase III · Shirur, Pune · Pride Landmarks

Promised for 31 Mar 2026, extended to 31 Jul 2026 — and that date has passed without the project marked complete on MahaRERA.

7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2026 to 31 Jul 2026.
  • Risk: The latest completion date on record, 31 Jul 2026, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate24 Jan 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100048886

Is Shikrapur Trade Center Phase III delayed?

Yes. MahaRERA records a promised completion of 31 Mar 2026, revised to 31 Jul 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100048886. The completion date moved from 31 Mar 2026 to 31 Jul 2026.

Who is the promoter?

MahaRERA records Pride Landmarks as the promoter of P52100048886.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100048886.