P52100048688
Audumbar Parvati by Gaurav Developers · Tathwade, Pune · Gaurav Developers
Promised for 4 Nov 2023, extended once to 30 Jul 2025 — and that date has passed without the project marked complete on MahaRERA.
2 years and 11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 4 Nov 2023 to 30 Jul 2025 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Jul 2025, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100048688
Is Audumbar Parvati by Gaurav Developers delayed?
Yes. MahaRERA records a promised completion of 4 Nov 2023, revised to 30 Jul 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100048688. The completion date moved from 4 Nov 2023 to 30 Jul 2025.
Who is the promoter?
MahaRERA records Gaurav Developers as the promoter of P52100048688.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100048688.