Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P52100048305

Pushpamedh · Parvati, Pune · Godse Shah Developers

Promised for 1 Jan 2027, extended to 1 May 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 1 Jan 2027 to 1 May 2027.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate26 Dec 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100048305

Is Pushpamedh delayed?

Its completion moved from 1 Jan 2027 to 1 May 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100048305. The completion date moved from 1 Jan 2027 to 1 May 2027.

Who is the promoter?

MahaRERA records Godse Shah Developers as the promoter of P52100048305.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100048305.

Answers are generated from the record.

Data through25 Oct 2026, 03:02SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology