Golden Aura Phase I · Lohgaon, Pune · Excel Homes
Promised for 31 Mar 2028, extended once to 31 Jul 2028, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Mar 2028 to 31 Jul 2028 (1 extension certificate on record).
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100047111
Is Golden Aura Phase I delayed?
Its completion moved from 31 Mar 2028 to 31 Jul 2028; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100047111. The completion date moved from 31 Mar 2028 to 31 Jul 2028.
Who is the promoter?
MahaRERA records Excel Homes as the promoter of P52100047111.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100047111.