DeregisteredMahaRERA status: Certificate Signed

P52100033872

Swapnalok Nagari, Bhor, Building No. 4 · Bhor, Pune · Swapnalok Developers

Promised for 31 Dec 2027 and not extended so far.

1 year and 2 months to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: MahaRERA lists this registration as deregistered.
  • Clear: Completion date never extended.

Documents 1

Registration certificate14 Mar 2022View

Orders 1

Deregistered

Deregistered: SWAPNALOK NAGARI, BHOR, BUILDING NO. 4

matched by RERA number

View order →

Questions about P52100033872

Is Swapnalok Nagari, Bhor, Building No. 4 delayed?

Not so far. MahaRERA records a promised completion of 31 Dec 2027, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100033872.

Who is the promoter?

MahaRERA records Swapnalok Developers as the promoter of P52100033872.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P52100033872.

Answers are generated from the record.