RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100032654
Runaa O2 · Mulshi, Pune · Runaa Homes
Promised for 31 Dec 2023, extended once to 31 May 2024 — and that date has passed without the project marked complete on MahaRERA.
2 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2023 to 31 May 2024 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 May 2024, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100032654
Is Runaa O2 delayed?
Yes. MahaRERA records a promised completion of 31 Dec 2023, revised to 31 May 2024, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100032654. The completion date moved from 31 Dec 2023 to 31 May 2024.
Who is the promoter?
MahaRERA records Runaa Homes as the promoter of P52100032654.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100032654.
Answers are generated from the record.
