Spring Valley · Hadapsar, Pune · R K Icon Associates
Promised for 30 Sep 2023, extended once to 29 Sep 2024 — and that date has passed without the project marked complete on MahaRERA.
3 years and 1 month past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Sep 2023 to 29 Sep 2024 (1 extension certificate on record).
- !Risk: The latest completion date on record, 29 Sep 2024, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100028832
Is Spring Valley delayed?
Yes. MahaRERA records a promised completion of 30 Sep 2023, revised to 29 Sep 2024, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100028832. The completion date moved from 30 Sep 2023 to 29 Sep 2024.
Who is the promoter?
MahaRERA records R K Icon Associates as the promoter of P52100028832.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100028832.