RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52100027063

Shree Nidhi · Lohgaon, Pune · Shree Infracon

Promised for 30 Jun 2023 — that date has passed and MahaRERA does not mark the project complete.

3 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Jun 2023, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate8 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100027063

Is Shree Nidhi delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100027063.

Who is the promoter?

MahaRERA records Shree Infracon as the promoter of P52100027063.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100027063.

Answers are generated from the record.

Data through25 Oct 2026, 02:43SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology