RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100027005
Govinda · Haveli, Pune · R J Brothers
Promised for 30 Jun 2024, extended once to 31 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.
2 years and 4 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2024 to 31 Dec 2025 (1 extension certificate on record).
- !Caution: The latest completion date on record, 31 Dec 2025, has passed.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100027005
Is Govinda delayed?
Yes. MahaRERA records a promised completion of 30 Jun 2024, revised to 31 Dec 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100027005. The completion date moved from 30 Jun 2024 to 31 Dec 2025.
Who is the promoter?
MahaRERA records R J Brothers as the promoter of P52100027005.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100027005.
Answers are generated from the record.