RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100026215

Gangajal Apartment · Lohgaon, Pune · Chagan Pralhad Bhagawat

Promised for 31 Mar 2021, extended once to 30 Sep 2022 — and that date has passed without the project marked complete on MahaRERA.

5 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2021 to 30 Sep 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Sep 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate30 Aug 2020View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100026215

Is Gangajal Apartment delayed?

Yes. MahaRERA records a promised completion of 31 Mar 2021, revised to 30 Sep 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100026215. The completion date moved from 31 Mar 2021 to 30 Sep 2022.

Who is the promoter?

MahaRERA records Chagan Pralhad Bhagawat as the promoter of P52100026215.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100026215.

Answers are generated from the record.

Data through25 Oct 2026, 02:42SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology