Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100025706

Saurabh Heights · Kesnand, Pune · Saurabh Construction

Promised for 30 Sep 2020, extended once to 30 Mar 2022 — and that date has passed without the project marked complete on MahaRERA.

6 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Sep 2020 to 30 Mar 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Mar 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate3 Jul 2020View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100025706

Is Saurabh Heights delayed?

Yes. MahaRERA records a promised completion of 30 Sep 2020, revised to 30 Mar 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100025706. The completion date moved from 30 Sep 2020 to 30 Mar 2022.

Who is the promoter?

MahaRERA records Saurabh Construction as the promoter of P52100025706.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100025706.

Answers are generated from the record.

Data through30 Oct 2026, 02:27SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology