RegisteredMahaRERA status: Certificate Signed
P52100025256
BramhaCorp Smart · Haveli, Pune · Bramhacorp Limited
Promised for 30 Dec 2026 and not extended so far.
2 months to go until the promised date.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P52100025256
Is BramhaCorp Smart delayed?
Not so far. MahaRERA records a promised completion of 30 Dec 2026, which has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P52100025256.
Who is the promoter?
MahaRERA records Bramhacorp Limited as the promoter of P52100025256.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100025256.
Answers are generated from the record.
Data through28 Oct 2026, 02:23SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology