P52100024458
Sai Shreeman · Pune (M Corp.), Pune · Sai Rj Constructions
Promised for 30 Dec 2023, extended once to 31 Dec 2027, which is still ahead.
The revised date is 4 years after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2023 to 31 Dec 2027 (1 extension certificate on record).
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100024458
Is Sai Shreeman delayed?
Its completion moved from 30 Dec 2023 to 31 Dec 2027; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100024458. The completion date moved from 30 Dec 2023 to 31 Dec 2027.
Who is the promoter?
MahaRERA records Sai Rj Constructions as the promoter of P52100024458.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100024458.