RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100024124

Forest View · Mohammadwadi, Pune · Seven Seas Developers

Promised for 30 Dec 2022, extended once to 30 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

3 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2022 to 30 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Dec 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate21 Jan 2020View
Extension certificate2 Apr 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100024124

Is Forest View delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2022, revised to 30 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100024124. The completion date moved from 30 Dec 2022 to 30 Dec 2024.

Who is the promoter?

MahaRERA records Seven Seas Developers as the promoter of P52100024124.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100024124.

Answers are generated from the record.

Data through25 Oct 2026, 02:40SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology