Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100023598
Opulent Properties Phase-II · Manjari Bk, Pune · Opulent Properties Phase Ii
Promised for 30 Dec 2022, extended once to 31 Jan 2029, which is still ahead.
The revised date is 6 years and 1 month after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2022 to 31 Jan 2029 (1 extension certificate on record).
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100023598
Is Opulent Properties Phase-II delayed?
Its completion moved from 30 Dec 2022 to 31 Jan 2029; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100023598. The completion date moved from 30 Dec 2022 to 31 Jan 2029.
Who is the promoter?
MahaRERA records Opulent Properties Phase Ii as the promoter of P52100023598.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100023598.