Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100023131

Amenity Space 1 - Navyangan Phase - II · Kasar Amboli, Pune · Avior Merlin Venture Llp

Promised for 28 Aug 2023, extended once to 27 Aug 2024 — and that date has passed without the project marked complete on MahaRERA.

3 years and 2 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 28 Aug 2023 to 27 Aug 2024 (1 extension certificate on record).
  • Caution: The latest completion date on record, 27 Aug 2024, has passed.

Documents 2

Registration certificate8 Sep 2021View
Extension certificate8 Sep 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100023131

Is Amenity Space 1 - Navyangan Phase - II delayed?

Yes. MahaRERA records a promised completion of 28 Aug 2023, revised to 27 Aug 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100023131. The completion date moved from 28 Aug 2023 to 27 Aug 2024.

Who is the promoter?

MahaRERA records Avior Merlin Venture Llp as the promoter of P52100023131.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100023131.

Answers are generated from the record.

Data through23 Oct 2026, 01:59SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology