RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100022945
Sharvari Homes · Undri, Pune · Vmg Buildcon
Promised for 14 Feb 2022, extended once to 14 Feb 2023 — and that date has passed without the project marked complete on MahaRERA.
4 years and 8 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 14 Feb 2022 to 14 Feb 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 14 Feb 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100022945
Is Sharvari Homes delayed?
Yes. MahaRERA records a promised completion of 14 Feb 2022, revised to 14 Feb 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100022945. The completion date moved from 14 Feb 2022 to 14 Feb 2023.
Who is the promoter?
MahaRERA records Vmg Buildcon as the promoter of P52100022945.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100022945.
Answers are generated from the record.