P52100019385
Chaitanya High Point · Baner, Pune · Chaitanya Developers
Promised for 30 Sep 2019, extended once to 29 Mar 2021 — and that date has passed without the project marked complete on MahaRERA.
7 years and 1 month past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Sep 2019 to 29 Mar 2021 (1 extension certificate on record).
- !Risk: The latest completion date on record, 29 Mar 2021, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100019385
Is Chaitanya High Point delayed?
Yes. MahaRERA records a promised completion of 30 Sep 2019, revised to 29 Mar 2021, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100019385. The completion date moved from 30 Sep 2019 to 29 Mar 2021.
Who is the promoter?
MahaRERA records Chaitanya Developers as the promoter of P52100019385.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100019385.