Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100018848

Sai Paradise · Lingali, Pune · Sj Construction

Promised for 30 Dec 2024, extended once to 30 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.

1 year and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2024 to 30 Dec 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Dec 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate2 May 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100018848

Is Sai Paradise delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2024, revised to 30 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100018848. The completion date moved from 30 Dec 2024 to 30 Dec 2025.

Who is the promoter?

MahaRERA records Sj Construction as the promoter of P52100018848.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100018848.

Answers are generated from the record.

Data through28 Oct 2026, 02:11SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology