RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100017943

90 Madhukunj · Bopodi, Pune · Gokhale Shelters Llp

Promised for 30 Mar 2023, extended once to 31 Jan 2024 — and that date has passed without the project marked complete on MahaRERA.

3 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Mar 2023 to 31 Jan 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Jan 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate22 Mar 2024View
Extension certificate22 Mar 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100017943

Is 90 Madhukunj delayed?

Yes. MahaRERA records a promised completion of 30 Mar 2023, revised to 31 Jan 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100017943. The completion date moved from 30 Mar 2023 to 31 Jan 2024.

Who is the promoter?

MahaRERA records Gokhale Shelters Llp as the promoter of P52100017943.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100017943.