Melange Residences · Bhoirwadi, Pune · Rama Synergy Spaces
Promised for 30 Sep 2021, extended once to 30 Mar 2023 — and that date has passed without the project marked complete on MahaRERA.
5 years and 1 month past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Sep 2021 to 30 Mar 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Mar 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100017090
Is Melange Residences delayed?
Yes. MahaRERA records a promised completion of 30 Sep 2021, revised to 30 Mar 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100017090. The completion date moved from 30 Sep 2021 to 30 Mar 2023.
Who is the promoter?
MahaRERA records Rama Synergy Spaces as the promoter of P52100017090.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100017090.