RegisteredExtendedMahaRERA status: Certificate Signed

P52100016845

ARV Royale Phase II · Hadapsar, Pune · Vedant Properties

Promised for 30 Dec 2026, extended to 30 Apr 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2026 to 30 Apr 2027.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate14 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100016845

Is ARV Royale Phase II delayed?

Its completion moved from 30 Dec 2026 to 30 Apr 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100016845. The completion date moved from 30 Dec 2026 to 30 Apr 2027.

Who is the promoter?

MahaRERA records Vedant Properties as the promoter of P52100016845.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100016845.

Answers are generated from the record.