Registered1 extensionMahaRERA status: Certificate Signed

P52100015727

Torna Mohar · Ambegaon Bk, Pune · Manoj Mandhare & Associates

Promised for 20 Dec 2024, extended once to 19 Dec 2028, which is still ahead.

The revised date is 4 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 20 Dec 2024 to 19 Dec 2028 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate20 Aug 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100015727

Is Torna Mohar delayed?

Its completion moved from 20 Dec 2024 to 19 Dec 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100015727. The completion date moved from 20 Dec 2024 to 19 Dec 2028.

Who is the promoter?

MahaRERA records Manoj Mandhare & Associates as the promoter of P52100015727.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100015727.

Answers are generated from the record.

Data through29 Oct 2026, 01:53SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology