P52100014561
Green Leaf · Pune (M Corp.), Pune · Kwality Developers
Promised for 31 Dec 2018, extended once to 30 Dec 2021 — and that date has passed without the project marked complete on MahaRERA.
7 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2018 to 30 Dec 2021 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Dec 2021, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100014561
Is Green Leaf delayed?
Yes. MahaRERA records a promised completion of 31 Dec 2018, revised to 30 Dec 2021, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100014561. The completion date moved from 31 Dec 2018 to 30 Dec 2021.
Who is the promoter?
MahaRERA records Kwality Developers as the promoter of P52100014561.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100014561.
Answers are generated from the record.