P52100014320
Sai Villa · Kolwadi, Pune · Jagdamba Enterprises And Construction
Promised for 31 Jan 2019, extended once to 30 Dec 2022 — and that date has passed without the project marked complete on MahaRERA.
7 years and 9 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Jan 2019 to 30 Dec 2022 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Dec 2022, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100014320
Is Sai Villa delayed?
Yes. MahaRERA records a promised completion of 31 Jan 2019, revised to 30 Dec 2022, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100014320. The completion date moved from 31 Jan 2019 to 30 Dec 2022.
Who is the promoter?
MahaRERA records Jagdamba Enterprises And Construction as the promoter of P52100014320.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100014320.
Answers are generated from the record.