Registered1 extensionMahaRERA status: Certificate Signed

P52100014063

Nanai Hights · Thergaon, Pune · Saisagar Properties

Promised for 31 Jan 2021, extended once to 31 Jan 2027, which is still ahead.

The revised date is 6 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Jan 2021 to 31 Jan 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 Feb 2025View
Extension certificate28 Feb 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100014063

Is Nanai Hights delayed?

Its completion moved from 31 Jan 2021 to 31 Jan 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100014063. The completion date moved from 31 Jan 2021 to 31 Jan 2027.

Who is the promoter?

MahaRERA records Saisagar Properties as the promoter of P52100014063.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100014063.

Answers are generated from the record.

Data through25 Oct 2026, 01:47SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology