Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100013632
Matoshree Park · Kondhve Dhawade, Pune · Dhawade Patil Infrastructure
Promised for 30 Sep 2023, extended once to 29 Sep 2024 — and that date has passed without the project marked complete on MahaRERA.
3 years and 1 month past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Sep 2023 to 29 Sep 2024 (1 extension certificate on record).
- !Caution: The latest completion date on record, 29 Sep 2024, has passed.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100013632
Is Matoshree Park delayed?
Yes. MahaRERA records a promised completion of 30 Sep 2023, revised to 29 Sep 2024, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100013632. The completion date moved from 30 Sep 2023 to 29 Sep 2024.
Who is the promoter?
MahaRERA records Dhawade Patil Infrastructure as the promoter of P52100013632.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100013632.
Answers are generated from the record.